PAST PROJECTS

1/5
1/4

 

East Gippsland Shire Council - Lucknow Wetlands and Drainage Project

 

Date: October 2014 - December 2015

 

Whelans completed the first major construction phases of the drainage strategy which consists of two large wetlands and a large drainage pipeline.

 

 

East Gippsland Shire Council
Eastern Creek Drainage Project

 

Date: June 2013 - February 2016


Eastern Creek is the main drainage line passing through Lakes Entrance. Whelans replaced numerous road crossings with large precast reinforced concrete crown units and in-situ slabs.

1/4

 

 

Kilmany Landfill

 

Date: October 2016 - March 2017

  
Capping of stage 1 and construction of cell 2
of the Kilmany landfill, including bulk earthworks and geosynthetic liners. 

 

 

V/Line Fernbank Bridge

 

Date: June 2016 

  
Procurement, fabrication and installation of a new concrete battle deck and concrete central piers replacing the existing superstructure and piers for the bridge 247.994km at Traralgon to Bairnsdale line (Fernbank)

 

 

McAlister & Wellsford Street
Widening Improvements

 

Date: November 2016 - January 2017

 
 McAlister & Wellsford Street widening improvements, Stratford. Including pavement,
 kerb and channel, and drainage works.
1/7
1/11
1/5

 

 

Falls Creek Road 24 Construction

 

Date: January 2011 - May 2011 

  
Rectification of two slips along the road, a major slip constructed using gabion and reinforced earth stabilisation and second slip constructed using soil reinforced stabilisation.

 

 

Wurruk - Sale Princes Highway Duplication 

 

Date: 2011 - 2013

 
Design and construction of the Princes Highway duplication between Wurruk and Sale. The project stretched 4.6km and included works for three roundabouts and eight bridges.
1/7

Bruthen - Nowa Nowa Rd, Township - Stage 6

 

Date: June 2006 - October 2007

  
Construction and realignment of Bruthen - Nowa Nowa Road including design and construction of a pedestrian bridge over Boggy Creek. The road is now the major B-double route through to Eastern Victoria and NSW.

 

Concrete Lining Culverts - Fernbank

 

Date: May 2016 - June 2016

Full reinforced concrete lining of ARMCO pipe culverts at 239.599km Sandy Creek and 241.805km on Bairnsdale line between Munro and Fernbank.
1/9
1/4

 

East Gippsland Water - Construction of Biosolids Storage

 

Date: June 2016 - September 2016

  
Construction of two Biosolids storage dams. This includes bulk earthworks, compaction and placement of clay and installation of a GCL.

 

 

Bega Valley Central Waste Facility - Stage 2

 

Date: 2015

 
Approx. 50,000m3 of bulk excavation, offsite disposal of 26,000 tonnes of excavated material, installation of a 12,600m2 lining system, installation of leachate drainage system and installation of leachate drainage aggregate.

 

Wellington Shire Council Road Works

 

Date: April 2016 - October 2016

 
Widening and rehabilitation of Hearthall Road, as well as associated drainage and intersection works.

 

Macks Creek Culvert Replacement, Colac

 

Date: 2014

 
Culvert replacement for V/Line at Macks Creek, 13km west of Colac on the Geelong - Warrnambool Rail Line. Construction service included the removal of the exisiting structure, placement of new precast components, in-situ concrete works, rock work and site reinstatement.
1/5
1/8

CURRENT PROJECTS

1/1

Princes Highway East Duplication

 

Date: October 2016 - May 2018


Design and construction of the Princes Highway East duplication between east of Nambrok Road and east of Maffra-Rosedale Road, Kilmany.

1/9

 

East Gippsland Road Maintenance Contract

 

Date: 2013 - 2019

 
Whelans Group is contracted to undertake the road maintenance for all East Gippsland Shire owned roads, covering approximately 10% of Victoria.
 

 

 

V/Line Box Culvert Replacement

 

Date: 2017

 
Bridge replacement with concrete box culvert arrangement at 187.961km on the Geelong-Warrnambool line, near Weerite.

 

Carpenter Street Culvert Upgrade

 

Date: April 2017 - May 2018

 

Construction service of the Carpenter Street culvert upgrade includes the removal of the existing structure, placement of new precast components, in-situ concrete works, rockwork and site reinstatement.​

 

Storm Water Drainage

 

Date: November 2016

 
Storm water drainage at Sale RAAF Base. This includes the installation of pipes, pits and headwalls.
1/1
 
 

WE MAKE IT HAPPEN

HEAD OFFICE

103 Rupert Street, Bairnsdale, Victoria 3875. 

Tel: (03) 5152 2844 

Fax: (03) 5152 7202   

ABN: 83 143 750 449
ACN: 143 750 449

Copyright@ 2017 | Whelans Group Investments Pty. Ltd.